Oracle Primavera - PM6 Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Thu, 2016-02-18 16:12 Permalink 2 thngs you are either 7 days 2 thngs you are either 7 days ahead of schedule or any new activities were added using a different calendar. Member for 21 years 9 months Member for 21 years 9 months Submitted by Jerome Odeh on Thu, 2016-02-18 13:39 Permalink Rasheed,Is your Finish Date Rasheed, Is your Finish Date the same date as it was 8 months ago? =jerome Member for 15 years 11 months Member for 15 years 11 months Submitted by Raymund de Laza on Thu, 2016-02-18 12:20 Permalink The default Calendar shall be The default Calendar shall be the same Calendar assigned to all Acyivities. Member for 11 years 6 months Member for 11 years 6 months Submitted by Olatayo on Thu, 2016-02-18 11:34 Permalink Thanks you Ronald but the Thanks you Ronald but the same default Calender was in use from the begining of the update. Do you have any other reason i may consider for this change. Hoping to hear from you soon Member for 22 years 7 months Member for 22 years 7 months Submitted by Ronald Weaver on Thu, 2016-02-18 01:21 Permalink I believe the summary bar I believe the summary bar duration is calculted using the Default Calendar. I would start there. Log in or register to post comments
Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Thu, 2016-02-18 16:12 Permalink 2 thngs you are either 7 days 2 thngs you are either 7 days ahead of schedule or any new activities were added using a different calendar.
Member for 21 years 9 months Member for 21 years 9 months Submitted by Jerome Odeh on Thu, 2016-02-18 13:39 Permalink Rasheed,Is your Finish Date Rasheed, Is your Finish Date the same date as it was 8 months ago? =jerome
Member for 15 years 11 months Member for 15 years 11 months Submitted by Raymund de Laza on Thu, 2016-02-18 12:20 Permalink The default Calendar shall be The default Calendar shall be the same Calendar assigned to all Acyivities.
Member for 11 years 6 months Member for 11 years 6 months Submitted by Olatayo on Thu, 2016-02-18 11:34 Permalink Thanks you Ronald but the Thanks you Ronald but the same default Calender was in use from the begining of the update. Do you have any other reason i may consider for this change. Hoping to hear from you soon
Member for 22 years 7 months Member for 22 years 7 months Submitted by Ronald Weaver on Thu, 2016-02-18 01:21 Permalink I believe the summary bar I believe the summary bar duration is calculted using the Default Calendar. I would start there.
Member for
16 years 3 months2 thngs you are either 7 days
2 thngs you are either 7 days ahead of schedule or any new activities were added using a different calendar.
Member for
21 years 9 monthsRasheed,Is your Finish Date
Rasheed,
Is your Finish Date the same date as it was 8 months ago?
=jerome
Member for
15 years 11 monthsThe default Calendar shall be
The default Calendar shall be the same Calendar assigned to all Acyivities.
Member for
11 years 6 monthsThanks you Ronald but the
Thanks you Ronald but the same default Calender was in use from the begining of the update.
Do you have any other reason i may consider for this change.
Hoping to hear from you soon
Member for
22 years 7 monthsI believe the summary bar
I believe the summary bar duration is calculted using the Default Calendar. I would start there.