Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

New Baseline

9 replies [Last post]
leighton rogers
User offline. Last seen 8 years 7 weeks ago. Offline
Joined: 9 Jan 2016
Posts: 15
Groups: None

Hi All,

 

I have had to change budgeted hours from my scedule i have had to take out nearly a third,  Should i now make a new baseline ?  If i do when should i do new baseline after next update etc?

 

Kind Regards

 

Leighton

Replies

leighton rogers
User offline. Last seen 8 years 7 weeks ago. Offline
Joined: 9 Jan 2016
Posts: 15
Groups: None

Hi Dieter

 

Yes I have xer copies from every week and update i have done luckily.

and i have put in notes on p6 that line manager and projext manager authorised reduction in hours.

Thankytou for your help.

 

 

Regards

 

Leighton

Dieter Wambach
User offline. Last seen 6 years 49 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350

Hi Leighton

Hopefully you copied the old plan - just for you.

If a manager reduces planned hours due to budget, ....

I've seen quite some planning engineers who were fired later after it was evident that the budgeted hours were too low. Can you take responsibility for the lower values?

Good luck!

Dieter

Dieter Wambach
User offline. Last seen 6 years 49 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350

Hi Leighton

Hopefully you copied the old plan - just for you.

If a manager reduces planned hours due to budget, ....

I've seen quite some planning engineers who were fired later after it was evident that the budgeted hours were too low. Can you take responsibility for the lower values?

Good luck!

Dieter

leighton rogers
User offline. Last seen 8 years 7 weeks ago. Offline
Joined: 9 Jan 2016
Posts: 15
Groups: None

Thanks for you reply very helpfull.  Much appreciated

Zoltan Palffy
User offline. Last seen 3 days 19 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

being over budget does not necessarily have anyhting to do with the end date.

You could have just under estimed the original budget.

Your performance is not what is should be. If this is the case why not ? What factors are causing poor perfomance.

If the client does not see cost or manhours then you can modify the cost and or manhours so that internally you reconcile your project. 

If you are using the manhours determine the durations then this is an entirely different topic. 

If you are concerned about the end and you are behind schedule on your on accord then you have 3 options

Option #1 Fast Tracking the Schedule 

Fast Tracking the schedule means to Revise the logic and do thing concurrently or in parallel which means that your manpower peak will be higher but it will be the same number of man-hours except for additional supervision.

A good rule of thumb is that sequential activities can sometimes be fast-tracked by up to 33%. In other words, if you're fast-tracking, you can start the second of two sequential activities when the first activity is 66% complete. So when you are 66% complete with the first conduit activity you can start the wire pulling.

Option #2 Crashing the Schedule

Crashing the schedule means to reduce your durations but you will have to increase your man-hours because you need more men to do it in a shorter amount of time. You would shorten the duration of the activities on the critical path by throwing additional resources to the critical path without necessarily getting the highest level of efficiency. You might have to do several iterations because you crash one critical path then something else becomes critical. You will have increased cost in with this option

Option #3 is using a combination of Tracking and Crashing.

leighton rogers
User offline. Last seen 8 years 7 weeks ago. Offline
Joined: 9 Jan 2016
Posts: 15
Groups: None

Hi Dieter ,

Yes it was my managers decision because it was way over budgeted , also it is a client project but they never see the baseline all they see is start, finish and % complete.  there is also no costing in this schedule basically the end date is the most important.

Thankyou for your reply.

 

Regards

 

Leighton

Dieter Wambach
User offline. Last seen 6 years 49 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350

Hi Leighton

Was this due to your or your boss' mistake? Then correct and create a new BL if the previous one was not yet issued.

Is it an internal or a customer project? Customer project: The BL must be approved and signed by the customer and your management. Internal: Management approval required if previous already published.

As Zoltan wrote: the BL is an important document. All future statusses of schedule will be compared with the BL - earned value, variances, milestones ....

Not that easy to answer without knowing the circumstances.

Good Planning

Dieter 

leighton rogers
User offline. Last seen 8 years 7 weeks ago. Offline
Joined: 9 Jan 2016
Posts: 15
Groups: None

Hi zoltan palffy

 

Thankyou for your advisw much appreciated.

 

Kind Regards

 

Leighton

Zoltan Palffy
User offline. Last seen 3 days 19 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

if the baseline has been approved then no you should not touch it which leads to the question why did you have to change your budgeted hours ? If it was an issued change then all the more reason to leave them in there to show the difference that is the whole point of establishing a baseline which is the original plan which you measure against. If you keep changing the baseline to match the current plan you have defeated the whole purpose of the baseline.