Oracle Primavera - PM6 Yes, Primaned found the Yes, Primaned found the solution! Issue was in MS project with options-->Schedule-->Calendar options. MSP indicated 31 days per month ... Primavera can only handle 30 days a month ... Quick fix, if you did any research, thanks! Sander G. Log in or register to post comments
Yes, Primaned found the Yes, Primaned found the solution! Issue was in MS project with options-->Schedule-->Calendar options. MSP indicated 31 days per month ... Primavera can only handle 30 days a month ... Quick fix, if you did any research, thanks! Sander G.
Yes, Primaned found the
Yes, Primaned found the solution!
Issue was in MS project with options-->Schedule-->Calendar options. MSP indicated 31 days per month ... Primavera can only handle 30 days a month ...
Quick fix, if you did any research, thanks!
Sander G.