Oracle Primavera - PM6 Member for 10 years 1 month Member for 10 years 1 month Submitted by makif61 on Tue, 2015-09-22 01:06 Permalink My email adress : My email adress : mthakif@gmail.com if you send me empty mail, ı will send xer file and cost accounts. Member for 15 years 11 months Member for 15 years 11 months Submitted by Raymund de Laza on Mon, 2015-09-21 10:52 Permalink Mehmet,Send me your XER file Mehmet, Send me your XER file and the Cost Accounts. Let me have your email add. Member for 10 years 1 month Member for 10 years 1 month Submitted by makif61 on Sun, 2015-09-20 20:45 Permalink Hi, I just import cost Hi, I just import cost account to P6 8.3 . Thanks for replying. Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Mon, 2015-09-14 19:20 Permalink what version do you have what version do you have ? cost accounts and expenses are two different things if you want to import cost accounts you need the Dictionary6x.xls expenses would be part of the activity6x.xls spreadsheet for SDK these are in reference to version 6 Log in or register to post comments
Member for 10 years 1 month Member for 10 years 1 month Submitted by makif61 on Tue, 2015-09-22 01:06 Permalink My email adress : My email adress : mthakif@gmail.com if you send me empty mail, ı will send xer file and cost accounts.
Member for 15 years 11 months Member for 15 years 11 months Submitted by Raymund de Laza on Mon, 2015-09-21 10:52 Permalink Mehmet,Send me your XER file Mehmet, Send me your XER file and the Cost Accounts. Let me have your email add.
Member for 10 years 1 month Member for 10 years 1 month Submitted by makif61 on Sun, 2015-09-20 20:45 Permalink Hi, I just import cost Hi, I just import cost account to P6 8.3 . Thanks for replying.
Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Mon, 2015-09-14 19:20 Permalink what version do you have what version do you have ? cost accounts and expenses are two different things if you want to import cost accounts you need the Dictionary6x.xls expenses would be part of the activity6x.xls spreadsheet for SDK these are in reference to version 6
Member for
10 years 1 monthMy email adress :
My email adress : mthakif@gmail.com
if you send me empty mail, ı will send xer file and cost accounts.
Member for
15 years 11 monthsMehmet,Send me your XER file
Mehmet,
Send me your XER file and the Cost Accounts. Let me have your email add.
Member for
10 years 1 monthHi, I just import cost
Hi, I just import cost account to P6 8.3 .
Thanks for replying.
Member for
16 years 3 monthswhat version do you have
what version do you have ?
cost accounts and expenses are two different things
if you want to import cost accounts you need the Dictionary6x.xls
expenses would be part of the activity6x.xls spreadsheet for SDK
these are in reference to version 6