Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

About knowing schedule % at certain date without schedule

1 reply [Last post]
mohamed abdalgawad
User offline. Last seen 7 years 30 weeks ago. Offline
Joined: 10 Nov 2011
Posts: 7
Groups: None

Hi Everyone

I hope everything is going just fine

Ok well, i have this problem iam sure there is a filter to do this to view BL values without press F9

without changing DD i want to look to my BL values 

Any Comment will be very much appreciated.

Replies

Zoltan Palffy
User offline. Last seen 3 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

I thought the quesiton was knowing the schedule % at a certain date wihtout schedue

just open the baseline and look 

what values  ?

without f9 there is no forward and backward pass without f9 there is no schedule with out f9 you might was well pack up and go home. forget about it, this does not compute, ANW Aint no way, what do you expect rubber biscuits ? GPS

 

if you want to look at resource values click on the resource tab and look at the values either units or costs