If as per the contract, only the BOQ amounts is allowed to be loaded in the programme, adding our internal expenses in the programme will increase the Total Budgeted Cost. This will not match with the Contract value and also can affect the Performance percentage complete.
Hi Kannan,Your question is
Hi Kannan,
Your question is interesting , I think we have options like Actual labour cost, Actual material cost, Actual total cost etc.
Also You have BL - Total cost (Excluding the indirect cost) . I think this will be enough for your EVA analysis.
Any other options / comments will be highly appreciated.
Best Regards
Sunil.
Hi Emily,If as per the
Hi Emily,
If as per the contract, only the BOQ amounts is allowed to be loaded in the programme, adding our internal expenses in the programme will increase the Total Budgeted Cost. This will not match with the Contract value and also can affect the Performance percentage complete.
Is there any solution to address this?
Thanks
Kannan