Oracle Primavera - PM6 Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Tue, 2014-12-02 14:11 Permalink your duration must be based your duration must be based something manhours cost whatever it may be so if you have 100 manhours for an activity and you have 50 manhours remaining your weighted duration % complete is 50% Log in or register to post comments
Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Tue, 2014-12-02 14:11 Permalink your duration must be based your duration must be based something manhours cost whatever it may be so if you have 100 manhours for an activity and you have 50 manhours remaining your weighted duration % complete is 50%
Member for
16 years 3 monthsyour duration must be based
your duration must be based something manhours cost whatever it may be
so if you have 100 manhours for an activity and you have 50 manhours remaining your weighted duration % complete is 50%