Forum Sponsor:

An innovation in P6 Professional training from RPCuk in partnership with Oracle. All the topics that matter to you in workshops customised to your role and industry.  Now get superior training value when you book our Blended Learning Bundle. Learn more here.

Viewer for .xer, xml and xls schedule files Schedule Reader™Free Trial

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Weighted duration% complete in P6

1 reply [Last post]
Anbin Ponnith
User offline. Last seen 3 years 21 weeks ago. Offline
Joined: 8 Jun 2009
Posts: 158

Dear All,

 

How do I get weighted duration % complete in P6

 

Regards,

Anbin

Replies

Zoltan Palffy
User offline. Last seen 5 days 18 hours ago. Offline
Joined: 13 Jul 2009
Posts: 2361
Groups: None

your duration must be based something manhours cost whatever it may be 

so if you have 100 manhours for an activity and you have 50 manhours remaining your weighted duration % complete is 50%