Level of effort activity

Member for

16 years 3 months

you can still put indirect manpower on it 

Member for

11 years 10 months

Well , so how i can assign such reourced ( eg. indirect manpower ) to an activity ??

Member for

16 years 3 months

LOE Activities only measure schedule performance as it relates to time no actual work effort.

Using a LOE to calculate earned value distorts the total project EVM becasue the values derived from LOE grows relative to the total project planned value

LOE does not distinguish cost variance from schedule variance. All variance is recognized as cost variance for LOE work