Oracle Primavera - PM6 Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Thu, 2014-10-23 13:33 Permalink yes click on the top of yes click on the top of activity id column and it will sort by activity id number you can also add any column that you wish to add Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Thu, 2014-10-23 13:33 Permalink yes click on the top of yes click on the top of activity id column and it will sort by activity id number you can also add any column that you wish to add Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Thu, 2014-10-23 13:33 Permalink yes click on the top of yes click on the top of activity id column and it will sort by activity id number you can also add any column that you wish to add Member for 11 years Member for 11 years Submitted by timmerman on Thu, 2014-10-23 04:01 Permalink Thanks, I honestly never Thanks, I honestly never knew you could do that. However it seems to give me the info the opposite way around from what I require. Is there anyway it can be sorted by Activity...then show the resources allocated to that activity? Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Wed, 2014-10-22 13:41 Permalink select Project then resource select Project then resource assignments then you can copy using control - C then paste to excel using control - V Log in or register to post comments
Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Thu, 2014-10-23 13:33 Permalink yes click on the top of yes click on the top of activity id column and it will sort by activity id number you can also add any column that you wish to add
Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Thu, 2014-10-23 13:33 Permalink yes click on the top of yes click on the top of activity id column and it will sort by activity id number you can also add any column that you wish to add
Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Thu, 2014-10-23 13:33 Permalink yes click on the top of yes click on the top of activity id column and it will sort by activity id number you can also add any column that you wish to add
Member for 11 years Member for 11 years Submitted by timmerman on Thu, 2014-10-23 04:01 Permalink Thanks, I honestly never Thanks, I honestly never knew you could do that. However it seems to give me the info the opposite way around from what I require. Is there anyway it can be sorted by Activity...then show the resources allocated to that activity?
Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Wed, 2014-10-22 13:41 Permalink select Project then resource select Project then resource assignments then you can copy using control - C then paste to excel using control - V
Member for
16 years 3 monthsyes click on the top of
yes click on the top of activity id column and it will sort by activity id number
you can also add any column that you wish to add
Member for
16 years 3 monthsyes click on the top of
yes click on the top of activity id column and it will sort by activity id number
you can also add any column that you wish to add
Member for
16 years 3 monthsyes click on the top of
yes click on the top of activity id column and it will sort by activity id number
you can also add any column that you wish to add
Member for
11 yearsThanks, I honestly never
Thanks,
I honestly never knew you could do that. However it seems to give me the info the opposite way around from what I require.
Is there anyway it can be sorted by Activity...then show the resources allocated to that activity?
Member for
16 years 3 monthsselect Project then resource
select Project
then resource assignments
then you can copy using control - C
then paste to excel using control - V