If an Activity is Task Driven the Original Duration for that activity may be 4 as displayed in the original duration field. Change the activity to Resource Driven and the original duration as displayed will change. I know why it changes, but what I am trying to do is to get it to display the 4. The client wants to see the "Activity Original Duration" not the "Resource Duration". I have a very difficult time trying to write and explain what I am asking. It is a big weakness. If you can understand me, I would appreciate any help. Thanks
Member for
11 years 1 monthThanks Mike...
Thanks Mike...
Member for
11 years 1 monthIf an Activity is Task Driven
If an Activity is Task Driven the Original Duration for that activity may be 4 as displayed in the original duration field. Change the activity to Resource Driven and the original duration as displayed will change. I know why it changes, but what I am trying to do is to get it to display the 4. The client wants to see the "Activity Original Duration" not the "Resource Duration". I have a very difficult time trying to write and explain what I am asking. It is a big weakness. If you can understand me, I would appreciate any help. Thanks
Member for
19 years 10 monthsHi RichardNormally the
Hi Richard
Normally the resource driver over rides the task.
This leads to all sorts of confusion if the two are out of sync - best keep them the same.
Best regards
Mike Testro