Open Ended Milestones

Member for

11 years 2 months

Hi Haroon,

You have one of two options:

1- assign a constrain on the activity to finish on/ afte/ before a certain given date

2- Link this activity to the final milestone of the project (for example finish project)

Regards

Aziz

Member for

18 years 9 months

Hi Haroon

This setting does only mean that if you'll filter for critical activities they'll be included to remind you to link them.

In your case this link is - as Mike wrote before - irrelevant. I wouldn't mark this option.

Regards

Dieter

Member for

19 years 10 months

Hi Haroon

If the "monitoring milestones" such as "receive all euipment" are not linked to something in the programme then are pointless unless they are just in place for reporting purposes or to trigger some sort of stage payment.

In which case any float is irelevant.

Best regards

Mike Testro

Member for

17 years

Hi Vladimir,

I forgot to mention that you should tick the "Make open-ended activities critical" under Schedule options.

 

-Haroon

Member for

24 years 8 months

Open ended activities in any case have huge total floats. They may be delayed up to project finish, so linking them with finish milestone does not increase their floats.

Member for

17 years

Hi Vladimir,

Linking like that will again generate huge Total float.

 

Haroon

Member for

24 years 8 months

If somebody will insist on No open ends link all open end milestones with project finish milestone.

Member for

17 years

Hello Dieter,

I will state it on the "Basis of Schedule/Schedule Assumptions" document.

Thank you for validating this method. I was worried if this was a taboo since everybody goes by the 'no-open-ends-except-first-and-last-activity' logic.

Haroon

 

P.S: yes, the same Haroon Al Rasheed ;)

Member for

18 years 9 months

Hi Haroon (Hārūn ar-Raschīd?)

Before you start your planning you write down all assumptions and discuss them with the PM. The use of open end control milestones for reporting purpose in my opinion is absolutely but must be part of this discussion and part of the planning procedure. Otherwise this might lead to misunderstandings.

Have a good planning

Dieter