Oracle Primavera - PM6 what you added are codes at what you added are codes at the project level NOT the activity level. To add codes at the activity level go to activities then select Enterprise then select activity codes. now you can assign the activities to these codes Robert, Project codes are Robert, Project codes are for projects and activity codes are for activities. Create activity codes to be assigned to an activity. Log in or register to post comments
what you added are codes at what you added are codes at the project level NOT the activity level. To add codes at the activity level go to activities then select Enterprise then select activity codes. now you can assign the activities to these codes
Robert, Project codes are Robert, Project codes are for projects and activity codes are for activities. Create activity codes to be assigned to an activity.
what you added are codes at
what you added are codes at the project level NOT the activity level. To add codes at the activity level go to activities then select Enterprise then select activity codes.
now you can assign the activities to these codes
Robert, Project codes are
Robert,
Project codes are for projects and activity codes are for activities.
Create activity codes to be assigned to an activity.