Project Finish becomes Early Finish After Scheduling.

Member for

16 years 3 months

have you set your project must finish by date  ?

Member for

16 years 7 months

1) What's your data date?

2) Do activites X or Y have any constrains on them? If so, what?

3) Any lag on the FS relationship between X and Y?

4) Also, under schedule options, can you confirm:

a) Is "use expected finish dates" ticked?

b) Retained logic, progress overide, or actual dates?

 

Cheers,



G

Member for

11 years 9 months

Sorry Joe, no, i am using the start & finish columns, i have only brough in the Early Start & Early Finish columns to investigate the issue.

Member for

11 years 7 months

Hi Lee,

 

If I understand your issue correctly. In P6 you are using the Early Finish and Late Finish columns and they will always show the original early and late finish dates even after actualizing the schedule.  Try using the Start and Finish columns which will give you the correct actual start and finish dates.  Also make sure to move your data date later than the actual start and actual finish dates before you F9.