If I understand your issue correctly. In P6 you are using the Early Finish and Late Finish columns and they will always show the original early and late finish dates even after actualizing the schedule. Try using the Start and Finish columns which will give you the correct actual start and finish dates. Also make sure to move your data date later than the actual start and actual finish dates before you F9.
Member for
16 years 3 monthshave you set your project
have you set your project must finish by date ?
Member for
16 years 7 months1) What's your data date?2)
1) What's your data date?
2) Do activites X or Y have any constrains on them? If so, what?
3) Any lag on the FS relationship between X and Y?
4) Also, under schedule options, can you confirm:
a) Is "use expected finish dates" ticked?
b) Retained logic, progress overide, or actual dates?
Cheers,
G
Member for
11 years 9 monthsSorry Joe, no, i am using the
Sorry Joe, no, i am using the start & finish columns, i have only brough in the Early Start & Early Finish columns to investigate the issue.
Member for
11 years 7 monthsHi Lee, If I understand
Hi Lee,
If I understand your issue correctly. In P6 you are using the Early Finish and Late Finish columns and they will always show the original early and late finish dates even after actualizing the schedule. Try using the Start and Finish columns which will give you the correct actual start and finish dates. Also make sure to move your data date later than the actual start and actual finish dates before you F9.