What version of Primavera are you using? Did you right click on the Labor Units Section of the screen and select Spreadsheet Fields - Budgeted Labor Units?
If yes, you may want to Try Assigning baseline again=Go to Project>Assign Baseline and assign baseline again. If this does not correct the problem, I need to know if the Remaining Quantity and Budgeted quantity are the same in the Activity Usage Spreadsheet.
Hi,Run a GC;If Planned
Hi,
Run a GC;
If Planned start/finish is not equal to blank
Then Planned start/finish equal to Start/Finish.
What you have to do is replace planned start and planned finish with start and finish.
- Ravi
Vinod,What version of
Vinod,
What version of Primavera are you using? Did you right click on the Labor Units Section of the screen and select Spreadsheet Fields - Budgeted Labor Units?
If yes, you may want to Try Assigning baseline again=Go to Project>Assign Baseline and assign baseline again. If this does not correct the problem, I need to know if the Remaining Quantity and Budgeted quantity are the same in the Activity Usage Spreadsheet.
Thanks