Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Primavera Update from xer file

No replies
Romany Aiad
User offline. Last seen 5 years 11 weeks ago. Offline
Joined: 6 Mar 2013
Posts: 8
Groups: None

How could i update a primvera file from another xer file if 

1- the 2 file have different wbs location (which mean than in the first xer file one level of the wbs is under wbs while in the other xer it is existing but under anther wbs )

2- we donot need to update the relationships

3-we need to update duration % of completion only