Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

How to filter activities progressing between two dates?

2 replies [Last post]
Pranab Kumar Deb
User offline. Last seen 4 years 6 weeks ago. Offline
Joined: 23 Jan 2007
Posts: 291

Hi All,

I want to filter activities between two dates in future, lets say 1June2014 and 30June2014. I am on P6.1, I would want to filter all activities including the ones having early dates inbetween and the ones progressing, i.e. started in April or May and progressing in June of 2014.

Thanks,

Pranab

  

Replies

Pranab Kumar Deb
User offline. Last seen 4 years 6 weeks ago. Offline
Joined: 23 Jan 2007
Posts: 291

Hi Jean,

Thank you for your reply!

It has to be

 

Early Start < 30June2014

Early Finish > 1Jun2014

 

 

Thanks a lot!

 

Pranab

Jean Desjardins
User offline. Last seen 9 years 21 weeks ago. Offline
Joined: 7 Nov 2011
Posts: 23
Groups: None

Create a filter "All of the following" with early start less than or equals June 30 2014 and late finish greater than or equals June 1st 2014