It’s common practice to use Primavera P6 Professional’s Time Distributed reports feature to create time-phased tables of data that are then exported to Microsoft Excel. However, if you’ve ever done this you may have noticed that in many cases the Subtotals row can be one column too far to the left. Here we show how to address this http://ow.ly/qot7K

Replies

Emily Foster
User offline. Last seen 22 hours 27 min ago. Offline
Joined: 19 Aug 2011
Posts: 573
Groups: None

Thansk Nick....I'm glad you liked it.

Anonymous
Groups: None

Useful link thanks