Welcome to Planning Planet, checkout the Guild of Project Controls Knowledge CAR

How to use Primavera P6's Time Distributed Reporting and Microsoft Excel

2 replies [Last post]
Emily Foster
User offline. Last seen 7 hours 1 min ago. Offline
Joined: 19 Aug 2011
Posts: 520
Groups: None

It’s common practice to use Primavera P6 Professional’s Time Distributed reports feature to create time-phased tables of data that are then exported to Microsoft Excel. However, if you’ve ever done this you may have noticed that in many cases the Subtotals row can be one column too far to the left. Here we show how to address this http://ow.ly/qot7K

Replies

Emily Foster
User offline. Last seen 7 hours 1 min ago. Offline
Joined: 19 Aug 2011
Posts: 520
Groups: None

Thansk Nick....I'm glad you liked it.

Nick Jackson
User offline. Last seen 6 weeks 3 days ago. Offline
Joined: 12 Jul 2007
Posts: 16
Groups: None

Useful link thanks