Filter activities that has changed compared to assigned basline

Member for

18 years 6 months

Hi Hakon,

Check this out

[[wysiwyg_imageupload:1741:]]

 

 

 

 

 

 

 

 

 

 

 

 

 

[[wysiwyg_imageupload:1742:]]

 

 

Cheers,

Arnold

Member for

13 years 1 month

thanx alot.

 

Haakon

Member for

13 years 1 month

Thanx, that works. Only thing i miss is that new activities (activities not in baseline, but in current project) seem to fall out. How can I include them?

Member for

18 years 8 months

Haakon

 

Filter on Baseline Start or Finish Variance

 

Regards

Member for

16 years 7 months

Filter on:

 

Where Variance - BL Project Finish date is not equal to 0

Or Variance - BL Project Start date is not equal to 0 

 

 

Cheers,



G