Oracle Primavera - PM6 Member for 13 years 7 months Member for 13 years 7 months Submitted by hmcleay on Tue, 2013-07-09 01:14 Permalink Aha!I see. The particular Aha! I see. The particular font I was using (MS Sans Serif) doesn't want to go any smaller than size 8. If I manually enter size 6, it doesn't change the size in the activities window, but it does change it in the print preview. It looks as though P6 doesn't fully support MS Sans Serif in sizes smaller than 8. However, there are a number of other fonts that are supported in smaller sizes. Problem solved! Thanks, Hugh. Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Mon, 2013-07-08 10:57 Permalink Hugh,In Primavera P6V7, Hugh, In Primavera P6V7, "Table Font and Row" lets you change the font size and color of the activities for all the screens in P6, not only the Print preview Log in or register to post comments
Member for 13 years 7 months Member for 13 years 7 months Submitted by hmcleay on Tue, 2013-07-09 01:14 Permalink Aha!I see. The particular Aha! I see. The particular font I was using (MS Sans Serif) doesn't want to go any smaller than size 8. If I manually enter size 6, it doesn't change the size in the activities window, but it does change it in the print preview. It looks as though P6 doesn't fully support MS Sans Serif in sizes smaller than 8. However, there are a number of other fonts that are supported in smaller sizes. Problem solved! Thanks, Hugh.
Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Mon, 2013-07-08 10:57 Permalink Hugh,In Primavera P6V7, Hugh, In Primavera P6V7, "Table Font and Row" lets you change the font size and color of the activities for all the screens in P6, not only the Print preview
Member for
13 years 7 monthsAha!I see. The particular
Aha!
I see. The particular font I was using (MS Sans Serif) doesn't want to go any smaller than size 8.
If I manually enter size 6, it doesn't change the size in the activities window, but it does change it in the print preview.
It looks as though P6 doesn't fully support MS Sans Serif in sizes smaller than 8.
However, there are a number of other fonts that are supported in smaller sizes.
Problem solved!
Thanks,
Hugh.
Member for
22 years 9 monthsHugh,In Primavera P6V7,
Hugh,
In Primavera P6V7, "Table Font and Row" lets you change the font size and color of the activities for all the screens in P6, not only the Print preview