Oracle Primavera - PM6 Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Fri, 2025-05-23 16:40 Permalink this is based on your this is based on your resource and what you have set for Default Units/Time if it is set to 8/d then it takes 8*the duration and give the manhours so fo the duration is 10 days the 8*10= 80 manhours or units you can change them manually or do them all at once then export to excel change the manhours save it then import back into P6 Member for 9 years 8 months Member for 9 years 8 months Submitted by David Kelly on Sun, 2025-01-12 10:07 Permalink A bit more detailed A bit more detailed explanation please, Cynthia. You add an actvity with what duration on what calendar Then you add a resouirce assignmnet record, with a resource on what calendar you add 100mhr into whiich field Which budegeted labour units field (resource or activity) then says 80, or is it both Log in or register to post comments
Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Fri, 2025-05-23 16:40 Permalink this is based on your this is based on your resource and what you have set for Default Units/Time if it is set to 8/d then it takes 8*the duration and give the manhours so fo the duration is 10 days the 8*10= 80 manhours or units you can change them manually or do them all at once then export to excel change the manhours save it then import back into P6
Member for 9 years 8 months Member for 9 years 8 months Submitted by David Kelly on Sun, 2025-01-12 10:07 Permalink A bit more detailed A bit more detailed explanation please, Cynthia. You add an actvity with what duration on what calendar Then you add a resouirce assignmnet record, with a resource on what calendar you add 100mhr into whiich field Which budegeted labour units field (resource or activity) then says 80, or is it both
Member for
16 years 3 monthsthis is based on your
this is based on your resource and what you have set for Default Units/Time if it is set to 8/d
then it takes 8*the duration and give the manhours
so fo the duration is 10 days the 8*10= 80 manhours or units
you can change them manually or do them all at once then export to excel change the manhours save it then import back into P6
Member for
9 years 8 monthsA bit more detailed
A bit more detailed explanation please, Cynthia.
You add an actvity with what duration on what calendar
Then you add a resouirce assignmnet record, with a resource on what calendar
you add 100mhr into whiich field
Which budegeted labour units field (resource or activity) then says 80, or is it both