Calendar is causing budget to change

Member for

16 years 3 months
Permalink

this is based on your resource and what you have set for Default Units/Time if it is set to 8/dthen it takes 8*the duration and give the manhours so fo the duration is 10 days the 8*10= 80 manhours or units you can change them manually or do them all at once then export to excel change the manhours save it then import back into P6

Member for

9 years 8 months
Permalink

A bit more detailed explanation please, Cynthia. You add an actvity with what duration on what calendarThen you add a resouirce assignmnet record, with a resource on what calendaryou add 100mhr into whiich fieldWhich budegeted labour units field (resource or activity) then says 80, or is it both