this is based on your resource and what you have set for Default Units/Time if it is set to 8/dthen it takes 8*the duration and give the manhours so fo the duration is 10 days the 8*10= 80 manhours or units you can change them manually or do them all at once then export to excel change the manhours save it then import back into P6
A bit more detailed explanation please, Cynthia. You add an actvity with what duration on what calendarThen you add a resouirce assignmnet record, with a resource on what calendaryou add 100mhr into whiich fieldWhich budegeted labour units field (resource or activity) then says 80, or is it both
this is based on your
this is based on your resource and what you have set for Default Units/Time if it is set to 8/dthen it takes 8*the duration and give the manhours so fo the duration is 10 days the 8*10= 80 manhours or units you can change them manually or do them all at once then export to excel change the manhours save it then import back into P6
A bit more detailed
A bit more detailed explanation please, Cynthia. You add an actvity with what duration on what calendarThen you add a resouirce assignmnet record, with a resource on what calendaryou add 100mhr into whiich fieldWhich budegeted labour units field (resource or activity) then says 80, or is it both