Resource User Defined Fields for different rates

2 replies [Last post]
Hermie LaO
User offline. Last seen 17 years 9 weeks ago. Offline
Joined: 27 Jan 2005
Posts: 29
Groups: None
In Open Plan you can have User Defined Fields in every resource.

Once practical use of this feature is being able to define different Unit costs.

One can be Internal Unit rate and the other can be Billible unit rate. Or any other rate/resource data you can think off!

This allows flexible Cost/Resource Reporting.

Nice huh!

Replies

John Owen
User offline. Last seen 9 years 14 weeks ago. Offline
Joined: 27 May 2005
Posts: 10
Groups: None
Using User Defined Fields to model multiple rates is limited to total values in Open Plan. To see/capture Time Phased values for multiple rates you would have to link the Open Plan schedule with Welcom’s Cobra cost management tool.
Frank Borcherdt
User offline. Last seen 7 years 19 weeks ago. Offline
Joined: 3 May 2001
Posts: 88
Groups: None
Can I assume it keeps the extended cost to date by period for each of these rates...otherwise its use is somewhat limited????