Finish Date Calculation Questions

Member for

18 years 11 months

Hi Casey,

Unlike the data date in P3/P6, MSP's status date does NOT enter into the schedule calculations.  In addition, there is no Original Duration, and the following always holds true: Duration = Actual Duration + Remaining Duration.

I expect MSP is calculating the finish date of 9/7/17 because that's what it was scheduled for already.

Updating the task status in MSP requires a bit more work than Primavera.  http://ronwinterconsulting.com/MS_Project_for_Construction.pdf

Good luck, tom