Microsoft Project Member for 15 years 9 months Member for 15 years 9 months Submitted by kumar s on Fri, 2012-09-07 02:15 Permalink thank you thank you Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Thu, 2012-09-06 11:12 Permalink Hello Kumar,MS Project takes Hello Kumar, MS Project takes its date formats from MS Windows; for instance, if MS Windows standard date format is MM/DD/YYYY, MS Project will display todays' date as "09/06/2012"; if the format is DD/MM/YYYY, the result is "06/09/2012" Alexandre Log in or register to post comments
Member for 15 years 9 months Member for 15 years 9 months Submitted by kumar s on Fri, 2012-09-07 02:15 Permalink thank you thank you
Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Thu, 2012-09-06 11:12 Permalink Hello Kumar,MS Project takes Hello Kumar, MS Project takes its date formats from MS Windows; for instance, if MS Windows standard date format is MM/DD/YYYY, MS Project will display todays' date as "09/06/2012"; if the format is DD/MM/YYYY, the result is "06/09/2012" Alexandre
Member for
15 years 9 monthsthank you
thank you
Member for
22 years 9 monthsHello Kumar,MS Project takes
Hello Kumar,
MS Project takes its date formats from MS Windows; for instance, if MS Windows standard date format is MM/DD/YYYY, MS Project will display todays' date as "09/06/2012"; if the format is DD/MM/YYYY, the result is "06/09/2012"