And tell me how about the values of ACWP, EAC? If they are different from 0, the reason is that you entered std. rate after saving baseline. Please check it again.
task baseline start baseline finish actual start actual finish
pcc 10.06.11 15.06.11 15.03.11 25.03.11
like i have a new start date for my project as it was delayed and we had got new start dates, but some work ahad commenced earlier.so this might be the reason or what.
task baseline start baseline finish actual start actual finish
pcc 10.06.11 15.06.11 15.03.11 25.03.11
like i have a new start date for my project as it was delayed and we had got new start dates, but some work ahad commenced earlier.so this might be the reason or what.
Member for
14 years 7 months
Member for14 years7 months
Submitted by Project Manager 67 on Sun, 2011-08-28 00:51
Member for
15 yearsAnd tell me how about the
And tell me how about the values of ACWP, EAC? If they are different from 0, the reason is that you entered std. rate after saving baseline. Please check it again.
Member for
17 years 5 monthsyes, i have done them. my
yes, i have done them. my case is like
task baseline start baseline finish actual start actual finish
pcc 10.06.11 15.06.11 15.03.11 25.03.11
like i have a new start date for my project as it was delayed and we had got new start dates, but some work ahad commenced earlier.so this might be the reason or what.
Member for
17 years 5 monthsyes, i have done them. my
yes, i have done them. my case is like
task baseline start baseline finish actual start actual finish
pcc 10.06.11 15.06.11 15.03.11 25.03.11
like i have a new start date for my project as it was delayed and we had got new start dates, but some work ahad commenced earlier.so this might be the reason or what.
Member for
14 years 7 monthsAre you sure you've baselined
Are you sure you've baselined the schedule and set the progress date prior to updating progress?