EV Cost and Schedule Indicators

Member for

15 years

And tell me how about the values of ACWP, EAC? If they are different from 0, the reason is that you entered std. rate after saving baseline. Please check it again.

Member for

17 years 5 months

yes, i have done them. my case is like

task  baseline start  baseline finish  actual start actual finish

pcc     10.06.11     15.06.11          15.03.11   25.03.11

like i have a new start date for my project as it was delayed and we had got new start dates, but some work ahad commenced earlier.so this might be the reason or what.

Member for

17 years 5 months

yes, i have done them. my case is like

task  baseline start  baseline finish  actual start actual finish

pcc     10.06.11     15.06.11          15.03.11   25.03.11

like i have a new start date for my project as it was delayed and we had got new start dates, but some work ahad commenced earlier.so this might be the reason or what.

Member for

14 years 7 months

Are you sure you've baselined the schedule and set the progress date prior to updating progress?