Thanks Alexandre, good point about rolling up to the Resource Names column, do you know where I might find an example of a macro that would do this please?
Thanks
Member for
22 years 9 months
Member for22 years9 months
Submitted by Alexandre Faul… on Wed, 2010-03-03 04:33
this indeed a FAQ! it is only possible to roll up resource names by writing a macro
however, I would not roll up my resource names in the Resource Name column, as it would duplicate the resource workload at work package (summary task) level; if necessary, use a custom text field instead
Member for
21 years 7 monthsRE: Roll Up Resource Names
MAYBE THIS IS WHAT YOU ARE LOOKING FOR.

Format the bar chart portion of a Gantt view:
http://office.microsoft.com/en-us/project/HA012253681033.aspx
Go to Display task names for individual .......
Have some issues with overlapping tasks, unless can be fully resolved I would avoid using this at all.
Hope this helps.
R. Davila
Member for
22 years 9 monthsRE: Roll Up Resource Names
Neil,
I remember having seen such a macro a few years ago, but I do not know were; thats too bad!
Have a look at the MSP newsgroups
Alexandre
Member for
15 years 7 monthsRE: Roll Up Resource Names
Thanks Alexandre, good point about rolling up to the Resource Names column, do you know where I might find an example of a macro that would do this please?
Thanks
Member for
22 years 9 monthsRE: Roll Up Resource Names
Neil,
this indeed a FAQ! it is only possible to roll up resource names by writing a macro
however, I would not roll up my resource names in the Resource Name column, as it would duplicate the resource workload at work package (summary task) level; if necessary, use a custom text field instead
Alexandre