Resorce Graph

Member for

22 years 9 months
Permalink

James,
quite the same in PWA; the chart is easily readable for few resources, and a nightmare if you have plenty
Cheers

Member for

19 years 5 months
Permalink

Gentlemen,

You can show multiple resources on one graph!! By using the Analyse Timescale Data in Excel, you can export all the resource data from the Resource Usage or Resource Sheet view. In Excel, you can then convert the data to a Stacked Histogram or Stacked Column. This will give a different colour for each resource, for each time-period.

I did this some time ago. It worked beautifully - but it took a little time. The only real problem is if you have lots of different resource names. The colours then become diffcult to differentiate.

James

Member for

22 years 9 months
Permalink

unfortunately not; it’s only possible by using MS Project Server and Project Web Access