Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Stretching Activity durations

7 replies [Last post]
Alex Costaras
User offline. Last seen 8 years 50 weeks ago. Offline
Joined: 30 May 2005
Posts: 13
Is there a way of stretching an activity’s duration in MSP. I’ve got a test activity that I want to span the gap between the earliest and latest equipment deliveries, but not as a hammock.

e.g.
......|Act A ======|
........................|Act B ==========|
Act C ===========================

What I need is for the duration of Act C to fluctuate as the predecessors change. But I want it to be a Task, not a summary bar or hammock

Replies

Will Russell
User offline. Last seen 12 years 15 weeks ago. Offline
Joined: 9 Apr 2003
Posts: 48
Groups: None
Me and my big mouth!! Of course you would only link the start of the first delivery task to the first milestone....doh!!

Will
Will Russell
User offline. Last seen 12 years 15 weeks ago. Offline
Joined: 9 Apr 2003
Posts: 48
Groups: None
Using the second technique as described by Sukumaran (very impressed with that by the way) you can link the start of all the delivery tasks to the first milestone and the finish of all the delivery tasks to the second milestone then it won’t matter which delivery is first or which delivery is last, the testing task will always show the duration over that whole period.
Will
Sukumaran Subaram...
User offline. Last seen 9 years 42 weeks ago. Offline
Joined: 2 Mar 2005
Posts: 229
Groups: GPC Malaysia
Create 2 dummy milestones. Link the earliest date and latest date to each milestone. Indent the milestone to create summary bar.

Highlight summary bar. Go to Format > Bar > Bar Shape. Remove start & end shapes. Change the middle bar to Task bar shape. Click OK and hide subtask.

Now when the predecessors change the duration for the above bar will fluctuate.

Regards.

Alex Costaras
User offline. Last seen 8 years 50 weeks ago. Offline
Joined: 30 May 2005
Posts: 13
Thanks zhang,

That did exactly what I wanted - you’re a star!
Zhang Haixiang
User offline. Last seen 4 years 30 weeks ago. Offline
Joined: 14 Apr 2005
Posts: 250
Groups: None
1. right click start date of actA, then click "Copy cell"
2. right click start date of actC, then click "paste special...", then click "Paste link"

do the same for finish date

hope this helps