Resource library is something you could say list of available resources that you can share with multiple projects. Here suppose you have different tickets from from different projects(software)then you can creat different schedule for each project and link with the resource library. Then you can analyse your resource availability to alocate for new tickets.
Do you mean start a brand new (blank) project with available Resource assigned, and then start entering task (Production Support Ticket) to it and then track the resource from there? (I never think of it that way!)
I dont know if you have found any software that would help you to develop your schedule.
If I understood correctly, you mean that once job comes (production support issue the ticket)your responcibility is to assign the resource to do it?
I think you can manage this with MSP or any other planning tool, I know that there is no straight way to do it but you could do using your skill and analysis with the available software.
With MSP, You should start with resource library then start listing the production support tickets issued and then assign resource. Before assigning resources you can check resource distribution.
I dont know if this would going to help becasue I never worked for Software Industry.
Thanks for your response. I feel the same way! Thats why I raised my question here hoping to get somebodys opinion, who has uses MSP to manage the type of tasks that I was talking about.
To be honest, I found MSP not the right answer for my situation, and I would like to confirm my thought.
Thanks,
Jarvis
Member for
20 years 11 months
Member for20 years11 months
Submitted by Philip Jonker on Wed, 2005-04-06 15:03
I Think I understand your problem. In the past, I have had various experiences with MSP, the most amazing was a project where we had to use the software despite the fact it could not handle the job, and we decided to bring in an MSP wizard, when we spoke about manhours, this wizard was clueless. MSP was developed for a niche in the marketplace, as a result it cannot perform, the basics required by normal project scheduling, when it comes to bigger stuff, hence, horses for courses.
When you work in the production industry, there is specific software for the purpose, and the same with projects. Do not think one tool is the answer to all questions. The problem is cost related, as the better tools is more expensive, due to the limited markets, and the amount of effort of input into the software. Decide whether you want a Porsche or a Volkswagen beetle.
Thank you for your efford and help. I think you dont really understand my question and you probably didnt work in the Software industry. Thanks for your help though.
Member for
20 years 7 months
Member for20 years8 months
Submitted by Sukumaran Suba… on Tue, 2005-04-05 05:55
The best way is discuss with your manager and engineers. Get them to brief you on the work sequences. Use this information to develop the preliminary schedule.
Once completed, print and circulate to your manager and engineers for their feedback. You got to do this few times to improvise and finalise the schedule.
Member for
20 years 7 months
Member for20 years8 months
Submitted by Sukumaran Suba… on Tue, 2005-04-05 02:56
Thank you for your response. I had been searching through the net to try to find some sample Project Plan files that show how to efficiently setup Software Support Related Task. But I didnt have much luck.... Can you point me to some resource that I can see some samples?
Thanks,
Jarvis
Member for
20 years 7 months
Member for20 years8 months
Submitted by Sukumaran Suba… on Tue, 2005-04-05 01:55
My question is relate to Production Software Support. For example when user raise an issue, a production support ticket will be created for me to assign resources to resolve the issue. Do you think MS Project is suitable to plan and track this type of task?
Member for
20 years 7 months
Member for20 years8 months
Submitted by Sukumaran Suba… on Mon, 2005-04-04 05:33
Production Support Related Task. Could you please elaborate about this project. Is it construction related work or production planning in industrial plant.
May be it will give some clear picture to other PPers and can give you a proper advise.
Member for
21 years 3 monthsRE: MS Project for Support Related Task?
Resource library is something you could say list of available resources that you can share with multiple projects. Here suppose you have different tickets from from different projects(software)then you can creat different schedule for each project and link with the resource library. Then you can analyse your resource availability to alocate for new tickets.
Member for
20 years 6 monthsRE: MS Project for Support Related Task?
Hi Raj,
Thanks for your hints.
Do you mean start a brand new (blank) project with available Resource assigned, and then start entering task (Production Support Ticket) to it and then track the resource from there? (I never think of it that way!)
What do you mean by Resource Library?
Thanks,
Jarvis
Member for
21 years 3 monthsRE: MS Project for Support Related Task?
Jarvis,
I dont know if you have found any software that would help you to develop your schedule.
If I understood correctly, you mean that once job comes (production support issue the ticket)your responcibility is to assign the resource to do it?
I think you can manage this with MSP or any other planning tool, I know that there is no straight way to do it but you could do using your skill and analysis with the available software.
With MSP, You should start with resource library then start listing the production support tickets issued and then assign resource. Before assigning resources you can check resource distribution.
I dont know if this would going to help becasue I never worked for Software Industry.
Member for
20 years 6 monthsRE: MS Project for Support Related Task?
Philip,
Thanks for your response. I feel the same way! Thats why I raised my question here hoping to get somebodys opinion, who has uses MSP to manage the type of tasks that I was talking about.
To be honest, I found MSP not the right answer for my situation, and I would like to confirm my thought.
Thanks,
Jarvis
Member for
20 years 11 monthsRE: MS Project for Support Related Task?
Hi Jarvis,
I Think I understand your problem. In the past, I have had various experiences with MSP, the most amazing was a project where we had to use the software despite the fact it could not handle the job, and we decided to bring in an MSP wizard, when we spoke about manhours, this wizard was clueless. MSP was developed for a niche in the marketplace, as a result it cannot perform, the basics required by normal project scheduling, when it comes to bigger stuff, hence, horses for courses.
When you work in the production industry, there is specific software for the purpose, and the same with projects. Do not think one tool is the answer to all questions. The problem is cost related, as the better tools is more expensive, due to the limited markets, and the amount of effort of input into the software. Decide whether you want a Porsche or a Volkswagen beetle.
Regards
Member for
20 years 6 monthsRE: MS Project for Support Related Task?
Hi there,
Thank you for your efford and help. I think you dont really understand my question and you probably didnt work in the Software industry. Thanks for your help though.
Member for
20 years 7 monthsRE: MS Project for Support Related Task?
The best way is discuss with your manager and engineers. Get them to brief you on the work sequences. Use this information to develop the preliminary schedule.
Once completed, print and circulate to your manager and engineers for their feedback. You got to do this few times to improvise and finalise the schedule.
Member for
20 years 7 monthsRE: MS Project for Support Related Task?
How about:
a) www.primavera.com for P3
b) www.astadev.com for Power Project / Team Play
c) www.welcom.com for Open Plan
Good Lucks.
Member for
20 years 6 monthsRE: MS Project for Support Related Task?
I get to that link already. None of those templates suit my needs... Are there any other place that provides sample template?
Member for
20 years 7 monthsRE: MS Project for Support Related Task?
Go to http://office.microsoft.com
Under Products (Home Page) click Project.
Under Browse Project (Project Page) click Templates. You can download all the related templates to develop your schedule.
Regards.
Member for
20 years 6 monthsRE: MS Project for Support Related Task?
Thank you for your response. I had been searching through the net to try to find some sample Project Plan files that show how to efficiently setup Software Support Related Task. But I didnt have much luck.... Can you point me to some resource that I can see some samples?
Thanks,
Jarvis
Member for
20 years 7 monthsRE: MS Project for Support Related Task?
Yes. MS Project is an user friendly tool. It is easy to setup the system and develop the schedule, as long as you keep the schedule simple.
If the task is to long i.e. 200 hours, then try to work out some details. Apply summary bar followed by detail tasks.
Member for
20 years 6 monthsRE: MS Project for Support Related Task?
My question is relate to Production Software Support. For example when user raise an issue, a production support ticket will be created for me to assign resources to resolve the issue. Do you think MS Project is suitable to plan and track this type of task?
Member for
20 years 7 monthsRE: MS Project for Support Related Task?
Hi Jarvis,
Production Support Related Task. Could you please elaborate about this project. Is it construction related work or production planning in industrial plant.
May be it will give some clear picture to other PPers and can give you a proper advise.
Regards.