There is one way is that update the activities but dont reschedule the balance work. Other way is define activity as fixed duration and put end date contraint and define the expected work(in hour or so) to be done during the whole period of work. So when ever you will update resource unit will fluctuate but duration will remain constant. Try this, hopefully it will work.
Member for
20 years 11 monthsRE: Maintenence schedule
Hi Raj
Thanks. Ill give it a try.
Regards, Gerry
Member for
21 years 3 monthsRE: Maintenence schedule
There is one way is that update the activities but dont reschedule the balance work. Other way is define activity as fixed duration and put end date contraint and define the expected work(in hour or so) to be done during the whole period of work. So when ever you will update resource unit will fluctuate but duration will remain constant. Try this, hopefully it will work.