Gantt Chart doesn’t spread out in Project 200

Member for

24 years 6 months

You may have manual calculation set. Press the F9 key to calcualte the schedule.



This setting is set by selecting Tools, Options, Calculation.



This is a system setting and affects all schedules opened on the machine and is not saved as a project setting, so the schedule may calculate automatically on another machine.



Paul E Harris

Eastwood Harris Pty Ltd

Planning and Scheduling Book Publishers

www.eh.com.au

Member for

16 years 9 months

I have already set (or MS Project sets) the constraint type to "as soon as possible" when I started out the project. The problem is still there unfortunately. Any other ideas?

Member for

16 years 9 months

HI Patrick,



Try checking constraint type. It might be set to early constraints. Replace your constraint type to as sson as possible constraint.



Hope this would help.