What if the owner caused delay is the same duration as the contractor caused delays - just in diff. timeframes?

No replies
John Reeves
User offline. Last seen 6 days 21 hours ago. Offline
Joined: 10 May 2013
Posts: 343
Groups: None

What if the owner caused delay is the same duration as the contractor caused delays - just in diff. timeframes?  Do you have the owner pay full OH fees and then contractor pays full liquidated damages?