Issue of IFC Drawings without full details.

Member for

14 years 11 months

Hi Mike,

Thank you for the reply making a task and updating the progress is the most feasible solution.

Best Regards,

Sunil

Member for

19 years 10 months

Hi Sunil

Therefore it remains at 0%.

You can put in a task leading to the milestone and measure progress on that.

Best regards

Mike Testro

Member for

14 years 11 months

Hi Mike,

Thanks for your timely reply. There are many mile stones as you have mentioned earlier. This is for substructure works only among that some footings are on hold. Since this is a milestone progress can be either 0% or 100% , but we cant put 100% because of the incomplete IFC details.

Best Regards,

Sunil.

Member for

19 years 10 months

Hi Sunil

Issued for construction drawings are rarely issued all at the same time so a single milestone is inappropriate.

Your programme should have a series of milestones for the latest dates for each section of the works with an allowance for sub contract design and procurement.

When these milestones are missed then you can assess the impact on completion for each case.

Remember that progress on a milestone is either 0% or 100%.

Best regards

Mike Testro