The right way to update as a sub contractor

Member for

19 years 10 months
Permalink

Hi JimmyYour extension of time relates only to your sub-contract work.The only reason you need to worry about the main contract completion date is if your own delys affect it.Best regardsMike Testro

Member for

11 years 9 months
Permalink

Hi Mike, thanks a lot. To your opinion of last para, considering there have alread some delay due to other issue when the design change released to us, should the EOT of this design change be the difference between impacted program end and the updated program end? (both of impacted program and updated program will came from the baseline with our activity affects/updates only as per your above opinion)

Member for

19 years 10 months
Permalink

Hi Jimmy - Welcome to Planning PlanetAs a sub-contractor you need to focus on your sub-contract work - you have no responsibility for anything else on the programme. So update your work and let the main contractor worry about the rest - including the contract completion date.You have a date to complete your sub-contract works within the whole baseline programme which will be interfaced with other sub-contractors. It is most likely that your sub-contract work will form part of the overall critical path but there will be no criticallity in your own work.If you encounter delays on your work such as design change then impact the event on the relevant task and your EoT entitlement will be the difference between the baseline sub-contract end and the impacted sub-contract end.Best regardsMike Testro