Force Majeure

Member for

17 years 2 months

Dear Mike and H.,



Yes clause 4.12 can apply in this case.

The Contractor must notify the Engineer, and the Engineer shall make the determination. The Engineer must also review the tender documents in this case per requirements of FIDIC clause 4.12.



H., do you have the Engineer determination regarding this case?



Best Regards,



Samer

Member for

19 years 10 months

Hi All



Sounds to me like a classic FIDIC clause 12 - unforeseen physical conditions - it does not just apply to groundworks.



Best regards



Mike Testro

Member for

22 years 11 months

We took the second time , to hit the supplier at head

Member for

19 years 1 month

but there’s always a hammer available on site i supposed?

Member for

22 years 11 months

Hi Trevor

It Was An Internal Fissure



You Cant See What Is Inside A 8’X 6’X 6’ Marble Block

And X Rays Are Not Normal In Marble Selctions



Thanks For All




Member for

17 years 2 months

Dear Hemanth,



What Trevor said is valid. You need to know what your Contract is saying. You need to go through all the clauses and identify the items related to unforeseen conditions as well.



Best Regards,



Samer

Member for

18 years 9 months

Hemanth



So the customer was involved. As even with greatest experience you can’t exclude a risk for an inclusion in a block of marble, what does the contract say - apart from FIDIC? Is a discussion possible with the customer to get an agreement? Check the items Samer wrote. I would ask an advocate for advice.



But still I can’t really believe the four weeks project’s delay.



Good luck!



Dieter

Member for

19 years 11 months

Hemanth,

I was asking questions in order to get sufficient information to provide solutions. If you don’t want to have the conversation just say so and I have better things to do.

If contractor wants to claim Force Majeure he must have to identify the Force Majeure event that caused the mysterious crack to appear between the inspection at the quarry and the final result on the site. Otherwise, the marble was ok at the quarry but got broken en-route while in the contractor’s control. Or, the inspection failed to find the flaw which existed at that time. Prove that and you have a case.

Member for

22 years 11 months

Dear Trevor

I was looking for solutions, not questions

inspection and approval of block by client at source was required as per contract (facilitated by contactor )



Dear Dieter

Customer approved the block at source



Dear Samer

Thank you Very Much

I will proceed with the points



Hemant

Member for

19 years 11 months

If a contractor is paid to source, procure, obtain, inspect, transport and install materials which meet a specified standard, and has control over that entire process, and has stated that he has the expertise to do it and takes responsibility for it, and that whole process falls apart, I would suggest that it is not Force Majeure.



Isn’t Force Majeure flood, fire, earthquake, tsunami, war etc?

Member for

17 years 2 months

Dear Hemanth,



Per FIDIC 1999, clause 19/1 In order to determine if the issue is Force Majeure or not, four items must be present:



1) Beyond the party’s control

Your case: yes



2) Party could not reasonably have provided against before entering into the Contract.

Answer: You need to prove that your % waste ordered was sufficient or over the industry norm.



3) having arisen, such party could not reasonably have avoided or overcome.

Answer: You need to prove that you remedy/ repair actions were the latest and it did not work.



4)not substantially attributable to the other part.

Answer: valid in your case.



If you have the necessary supporting documents, then yes you can consider it as force majeure since the four conditions are all present.



Best Regards,



Samer


Member for

18 years 9 months

Hemanth

If you work with marble, you know there is a big risk for inclusions. Why didn’t you include the customer into inspection - would have been a nice journey to Italy for him as well.

What I can’t understand: Italian marble in general is used for decoration purpose - can be mounted later. Did you really have to stop all work for those 4 weeks - strange?



Dieter

Member for

19 years 11 months

Does client say why?

Do you think should be yes? Why?