The Contractor must notify the Engineer, and the Engineer shall make the determination. The Engineer must also review the tender documents in this case per requirements of FIDIC clause 4.12.
H., do you have the Engineer determination regarding this case?
What Trevor said is valid. You need to know what your Contract is saying. You need to go through all the clauses and identify the items related to unforeseen conditions as well.
Best Regards,
Samer
Member for
18 years 9 months
Member for18 years9 months
Submitted by Dieter Wambach on Mon, 2009-02-09 01:45
So the customer was involved. As even with greatest experience you cant exclude a risk for an inclusion in a block of marble, what does the contract say - apart from FIDIC? Is a discussion possible with the customer to get an agreement? Check the items Samer wrote. I would ask an advocate for advice.
But still I cant really believe the four weeks projects delay.
Good luck!
Dieter
Member for
19 years 11 months
Member for19 years11 months
Submitted by Trevor Rabey on Mon, 2009-02-09 00:33
I was asking questions in order to get sufficient information to provide solutions. If you dont want to have the conversation just say so and I have better things to do.
If contractor wants to claim Force Majeure he must have to identify the Force Majeure event that caused the mysterious crack to appear between the inspection at the quarry and the final result on the site. Otherwise, the marble was ok at the quarry but got broken en-route while in the contractors control. Or, the inspection failed to find the flaw which existed at that time. Prove that and you have a case.
Member for
22 years 11 months
Member for23 years
Submitted by Hemanth Kumar on Sun, 2009-02-08 23:39
If a contractor is paid to source, procure, obtain, inspect, transport and install materials which meet a specified standard, and has control over that entire process, and has stated that he has the expertise to do it and takes responsibility for it, and that whole process falls apart, I would suggest that it is not Force Majeure.
Isnt Force Majeure flood, fire, earthquake, tsunami, war etc?
Member for
17 years 2 months
Member for17 years3 months
Submitted by Samer Zawaydeh on Sat, 2009-02-07 14:42
If you work with marble, you know there is a big risk for inclusions. Why didnt you include the customer into inspection - would have been a nice journey to Italy for him as well.
What I cant understand: Italian marble in general is used for decoration purpose - can be mounted later. Did you really have to stop all work for those 4 weeks - strange?
Dieter
Member for
19 years 11 months
Member for19 years11 months
Submitted by Trevor Rabey on Sat, 2009-02-07 04:31
Member for
17 years 2 monthsRE: Force Majeure
Dear Mike and H.,
Yes clause 4.12 can apply in this case.
The Contractor must notify the Engineer, and the Engineer shall make the determination. The Engineer must also review the tender documents in this case per requirements of FIDIC clause 4.12.
H., do you have the Engineer determination regarding this case?
Best Regards,
Samer
Member for
19 years 10 monthsRE: Force Majeure
Hi All
Sounds to me like a classic FIDIC clause 12 - unforeseen physical conditions - it does not just apply to groundworks.
Best regards
Mike Testro
Member for
22 years 11 monthsRE: Force Majeure
We took the second time , to hit the supplier at head
Member for
19 years 1 monthRE: Force Majeure
but theres always a hammer available on site i supposed?
Member for
22 years 11 monthsRE: Force Majeure
Hi Trevor
It Was An Internal Fissure
You Cant See What Is Inside A 8X 6X 6 Marble Block
And X Rays Are Not Normal In Marble Selctions
Thanks For All
Member for
17 years 2 monthsRE: Force Majeure
Dear Hemanth,
What Trevor said is valid. You need to know what your Contract is saying. You need to go through all the clauses and identify the items related to unforeseen conditions as well.
Best Regards,
Samer
Member for
18 years 9 monthsRE: Force Majeure
Hemanth
So the customer was involved. As even with greatest experience you cant exclude a risk for an inclusion in a block of marble, what does the contract say - apart from FIDIC? Is a discussion possible with the customer to get an agreement? Check the items Samer wrote. I would ask an advocate for advice.
But still I cant really believe the four weeks projects delay.
Good luck!
Dieter
Member for
19 years 11 monthsRE: Force Majeure
Hemanth,
I was asking questions in order to get sufficient information to provide solutions. If you dont want to have the conversation just say so and I have better things to do.
If contractor wants to claim Force Majeure he must have to identify the Force Majeure event that caused the mysterious crack to appear between the inspection at the quarry and the final result on the site. Otherwise, the marble was ok at the quarry but got broken en-route while in the contractors control. Or, the inspection failed to find the flaw which existed at that time. Prove that and you have a case.
Member for
22 years 11 monthsRE: Force Majeure
Dear Trevor
I was looking for solutions, not questions
inspection and approval of block by client at source was required as per contract (facilitated by contactor )
Dear Dieter
Customer approved the block at source
Dear Samer
Thank you Very Much
I will proceed with the points
Hemant
Member for
19 years 11 monthsRE: Force Majeure
If a contractor is paid to source, procure, obtain, inspect, transport and install materials which meet a specified standard, and has control over that entire process, and has stated that he has the expertise to do it and takes responsibility for it, and that whole process falls apart, I would suggest that it is not Force Majeure.
Isnt Force Majeure flood, fire, earthquake, tsunami, war etc?
Member for
17 years 2 monthsRE: Force Majeure
Dear Hemanth,
Per FIDIC 1999, clause 19/1 In order to determine if the issue is Force Majeure or not, four items must be present:
1) Beyond the partys control
Your case: yes
2) Party could not reasonably have provided against before entering into the Contract.
Answer: You need to prove that your % waste ordered was sufficient or over the industry norm.
3) having arisen, such party could not reasonably have avoided or overcome.
Answer: You need to prove that you remedy/ repair actions were the latest and it did not work.
4)not substantially attributable to the other part.
Answer: valid in your case.
If you have the necessary supporting documents, then yes you can consider it as force majeure since the four conditions are all present.
Best Regards,
Samer
Member for
18 years 9 monthsRE: Force Majeure
Hemanth
If you work with marble, you know there is a big risk for inclusions. Why didnt you include the customer into inspection - would have been a nice journey to Italy for him as well.
What I cant understand: Italian marble in general is used for decoration purpose - can be mounted later. Did you really have to stop all work for those 4 weeks - strange?
Dieter
Member for
19 years 11 monthsRE: Force Majeure
Does client say why?
Do you think should be yes? Why?