Clause 52.2 FIDIC 4th Edition

1 reply [Last post]
Omer Hassan
User offline. Last seen 15 years 33 weeks ago. Offline
Joined: 6 Jul 2008
Posts: 18
Groups: None
I have one very simple question that power of Engineer to Fix rate as per clause 52.2 of FIDIC is applicable on whole quantity or on only varied work?

Employer add following clause in CoC part-II clause 52.2 FIDIC 4th Edition

“Provided further that no change in the rate or price for any item contained in the Contract shall be considered unless such item accounts for an amount more than 2 percent of the Contract Price as stated in the Letter of Acceptance and the actual quantity of work executed under the item exceeds or falls short of the quantity set out in the Bill of Quantities by more than 25 percent.”

Now in this case if new rates are applied then does it applicable on whole quantity or on only varied quantity?

Please provide the answers with contractual reference

Regards,
Omer

Replies

Andrew Flowerdew
User offline. Last seen 2 years 23 weeks ago. Offline
Joined: 14 Dec 2004
Posts: 960
Groups: None
Omer,

Have fun reading:

http://www1.fidic.org/faq/searchfaq.asp?expand=yes&fldauto=145&inc=22%2E...

The clause says the Engineer shall fix the rate or price for an item - strongly arguable that it applies to the whole quantity covered by that item.

But the reason for the rate to be inappropriate has to be because of the varied work.