Interpretation of Updating a Contract Program

Member for

18 years 3 months

Over time the programme will change due to things you didn’t include that you should have, clients instructions to carry extra works and other unforeseen circumstances. You need to read the contract conditions at to what you have to do to get the program pass the client but a programme is a live document. Look at it this way, something changes and you don’t change the program. You might as well just throw it in the bin as the programme does not reflect what you are doing. Make the changes and tell the client what they are, its up for approval so all he can do is reject it. Work with him to get it approved if not you could go a long time without an approved programme and that isn’t good in anybody’s book.

Member for

20 years 4 months

Vijay,



Please clarify if we are discussing a programme that is pursuant to a clause in the contract (FIDIC Clause 14.1, for example) or a document which is specifically identified as a ’Contract Document’ and therefore prioritised in the Contract Documentation Clause of the Conditions of Contract (5.2?)



If the program is to be produced pursuant to Clause 14.1 then it IS NOT a Contract Programme, it does not require approval only ’Consent for Use’.



In this case you can update the programme in tems of progress, logic and delay and submit it in line with the report specification.



Don’t try to hash the programme though, only change the logic if it works, don’t delete it because it’s in the way, you’ll suffer later in the project.



D.

Member for

20 years 6 months

If its a contract programme you can’t change any link without the Engineer’s approval.



But ofcourse in your monthly report you can modify it along with the comments on your changes.