Use or not of a consented schedule in a Claim

Member for

20 years 6 months

Yes I also agree.



Although the engineer had not consent on the revised schedule. The original schedule was based on certain scope of work and subsequent change orders issued to him will form the part of document.



Infact revised plan submitted could become a "Proposed Recovery Plan" by the contractor.

Member for

20 years 5 months

The contractor can claim anything though he has to timely reserve his right for doing so. This ’reservation of right’ has to be done within a specified time after the event has occurred, sometime 7 or 14 days.

I believe you are using FIDIC and if I remember correctly the notices are mentioned under clause 53.



Theoretically, if the contractor has not reserved his right for claiming for an event he can’t wake up after 6 months and place his claim. Though practically I have seen that it can be done but with a difficulty.



Regards

Rashid Iqbal

Member for

24 years 4 months

In my view, yes.



The Contractor’s revised schedule represented his ’plan’ as to how he was going to modify his original programme and absorb the Employer’s changes. Subsequent changes and delays should be measured against the revised programme to show the further effect.



Roger Gibson