Time to Go Column & Hiding duration for the summary line

Member for

6 years 1 month

Thank you for your reply, I couldnt reflect the changes to the summary headings. Could you please show me steps if you dont mind? Also, for the time to go column, do you have any idea how to insert it?

Thank you,

Kind regards,

Yarkin

Member for

13 years 9 months

Hi Yarkin,

It looks like your view has a sort on it.  If so, the setting to hide column details on a sort is within the Sort/Group Properties:

[[wysiwyg_imageupload:7468:]]

You will need to chose "Sub-heading with only name column" to get the desired view.

Thanks,

Ben @ Powerproject