Negative float applies to chain

2 replies [Last post]
Daniel Zepko
User offline. Last seen 5 years 51 weeks ago. Offline
Joined: 28 Jun 2017
Posts: 7
Groups: None

I am fairly new to Asta Project Planner, I am troubled that the contractor has submitted a schedule indicating activities with remining durations indicate finish dates prior to the data date.

For example, one activity indicated a remaing duration of 10days; however, the activity was shown completing on September 27, 2017  or prior the progress date or data date of OCT 1, 2017.

I should note the activity finishing September 27, 2017 was also indicating -20 days float (however the completion date of the project was maintained). I am aware there is an option under reschedule (Negative Float Applies to Chain) to show this true status of the schedule which is behind schedule. 

However i am wordering why this option is available, it goes against everything i thought i knew about scheduling. It is also appears that the Contractor was not aware of this option and/or just didn't reveiw the update before submittal.

I dont recall seeing any discussions on the PP forum concering this issues so i would like to open it up for discussions.

 

Thanks

Dan

Replies

Andrew Pearce
User offline. Last seen 1 year 14 weeks ago. Offline
Joined: 11 Jun 2001
Posts: 175

Hi Daniel,

Are you reviewing a PDF or soft copy of the schedule?

I suspect that the file has not been rescheduled to the progress update date.

Mike Testro
User offline. Last seen 5 weeks 1 day ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Daniel

I do not recognise that situation in any aspect of asta Powerproject.

The software does not schedule negative float but flags up a warning that it has been created and will not continue until the blockage has been removed.

Best regards

Mike T