If your programme has 'heirachy' to it (i.e. a number of summaries or expanded tasks), fonts and cell colours can be set at a heirachy level to help you clearly display the various levels. Therefore, these settings may be overriding your table defaults.
Check 'Hierachy Appearance' from the 'Format' ribbon to see what these are set to for each level of the programme.
If that doesn't help, feel free to contact our support team via support@elecosoft.com.
Member for
8 years 4 monthsBen, Many thanks for your
Ben,
Many thanks for your response, I have managed to amend them that way.
Thank You
Dom
Member for
13 years 9 monthsHi Dom, If your programme has
Hi Dom,
If your programme has 'heirachy' to it (i.e. a number of summaries or expanded tasks), fonts and cell colours can be set at a heirachy level to help you clearly display the various levels. Therefore, these settings may be overriding your table defaults.
Check 'Hierachy Appearance' from the 'Format' ribbon to see what these are set to for each level of the programme.
If that doesn't help, feel free to contact our support team via support@elecosoft.com.
Thanks,
Ben @ Asta Powerproject
Member for
19 years 10 monthsHi Dominic - Welcome to
Hi Dominic - Welcome to planning planet.
Right Click on the column you wish to change.
Select Format cells - Select the Font dialogue - make your selection.
Best regards
Mike Testro