Hi Andy - welcome to planning planet.

There are two ways.

1. Use the histogram software built into the system - this is best if you want to demonstrate a histogram under a project view. Look in the Help section for full instructions.

2. Export the histogram data to excell and use that to generate the graphs - this gives you better flexibility and presentation options.

Best regards

Mike Testro