Baseline Vs Actual Progress in Line of Balance

Member for

15 years 8 months

Dear,

 

The problem is whether this could be shown in Line of Balance rather than in Gannt Chart.

Of course, this could be done in Gannt Chart.

 

Thank!

 

Regards,

 

Gary Lo

Member for

11 years 2 months

Hai Gary,

hope the question is how to show the base line and actual progress(ahead/delay) in the same time

for that you have to

1.Maintain the base line of the program 

Project Menu>maintain Baseline>add>Save a copy of the current project

2.Assign Baseline

Project Menu>Project Baseline>''select your program''  and Primary Baseline>''select your program''

 

   Dont forget to tick the primary Baseline display options in the Bars in gantt chart

 

Thanks

VL