Asta Powerproject Member for 15 years 8 months Member for 15 years 8 months Submitted by Lo Gary on Sun, 2016-04-10 15:33 Permalink Dear, The problem is whether Dear, The problem is whether this could be shown in Line of Balance rather than in Gannt Chart. Of course, this could be done in Gannt Chart. Thank! Regards, Gary Lo Member for 11 years 2 months Member for 11 years 2 months Submitted by lal on Sun, 2016-04-10 12:58 Permalink Hai Gary,hope the question is Hai Gary, hope the question is how to show the base line and actual progress(ahead/delay) in the same time for that you have to 1.Maintain the base line of the program Project Menu>maintain Baseline>add>Save a copy of the current project 2.Assign Baseline Project Menu>Project Baseline>''select your program'' and Primary Baseline>''select your program'' Dont forget to tick the primary Baseline display options in the Bars in gantt chart Thanks VL Log in or register to post comments
Member for 15 years 8 months Member for 15 years 8 months Submitted by Lo Gary on Sun, 2016-04-10 15:33 Permalink Dear, The problem is whether Dear, The problem is whether this could be shown in Line of Balance rather than in Gannt Chart. Of course, this could be done in Gannt Chart. Thank! Regards, Gary Lo
Member for 11 years 2 months Member for 11 years 2 months Submitted by lal on Sun, 2016-04-10 12:58 Permalink Hai Gary,hope the question is Hai Gary, hope the question is how to show the base line and actual progress(ahead/delay) in the same time for that you have to 1.Maintain the base line of the program Project Menu>maintain Baseline>add>Save a copy of the current project 2.Assign Baseline Project Menu>Project Baseline>''select your program'' and Primary Baseline>''select your program'' Dont forget to tick the primary Baseline display options in the Bars in gantt chart Thanks VL
Member for
15 years 8 monthsDear, The problem is whether
Dear,
The problem is whether this could be shown in Line of Balance rather than in Gannt Chart.
Of course, this could be done in Gannt Chart.
Thank!
Regards,
Gary Lo
Member for
11 years 2 monthsHai Gary,hope the question is
Hai Gary,
hope the question is how to show the base line and actual progress(ahead/delay) in the same time
for that you have to
1.Maintain the base line of the program
Project Menu>maintain Baseline>add>Save a copy of the current project
2.Assign Baseline
Project Menu>Project Baseline>''select your program'' and Primary Baseline>''select your program''
Dont forget to tick the primary Baseline display options in the Bars in gantt chart
Thanks
VL