Line of Balance

Member for

15 years 8 months
Permalink

Dear,

 

Could I export the line of balance graph to Excel to make modification?

 

 

Regards,

 

Gary Lo

Member for

15 years 8 months
Permalink

Dear,

 

Could I have both the line of balance baseline  and actual progress be shown at the same time?

 

 

 

 

Regards,

 

 

Gary Lo

Member for

13 years 9 months
Permalink

Hi Gary Lo,

Yes - on your Line of Balance graph, right-click and chose "Show Standalone".  This opens a new tab within Asta Powerproject with the gantt chart toggled off.  If you now look at Print Preview, you will see that only the LoB graph is included in your print out.

Thanks,

Ben @ Asta Powerproject