Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Re-Schedule

2 replies [Last post]
Ronan Niland
User offline. Last seen 6 years 40 weeks ago. Offline
Joined: 21 Jun 2012
Posts: 10
Groups: None

I have been given a programme to review. It Asta V12. When I re-schedule, I find 2 tasks that have

  1. No Links (in or out)
  2. No constraints of any kind

After I re-schedule (F9), the tasks “just sit there”. They do not move back to the re-schedule date. I can “move” them to another date, and again they just sit there. What is causing this??

Ronan

Replies

Ronan Niland
User offline. Last seen 6 years 40 weeks ago. Offline
Joined: 21 Jun 2012
Posts: 10
Groups: None

Thanks

Mike Testro
User offline. Last seen 6 weeks 1 day ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Ronan

Goto Tools > Options > Reschedule and you will see three options for tasks with no links.

Yours is pobably set to > "Leave as drawn within constraints"

Choose any of the other two to get a different option - the task will probaly fall back to day 1.

Best option is to put some logic onto it.

Best regards

Mike Testro