Asta Powerproject Member for 13 years 4 months Member for 13 years 4 months Submitted by Ronan on Wed, 2012-12-19 05:50 Permalink Thanks Thanks Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Fri, 2012-12-14 09:02 Permalink Hi Ronan Goto Tools > Options Hi Ronan Goto Tools > Options > Reschedule and you will see three options for tasks with no links. Yours is pobably set to > "Leave as drawn within constraints" Choose any of the other two to get a different option - the task will probaly fall back to day 1. Best option is to put some logic onto it. Best regards Mike Testro Log in or register to post comments
Member for 13 years 4 months Member for 13 years 4 months Submitted by Ronan on Wed, 2012-12-19 05:50 Permalink Thanks Thanks
Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Fri, 2012-12-14 09:02 Permalink Hi Ronan Goto Tools > Options Hi Ronan Goto Tools > Options > Reschedule and you will see three options for tasks with no links. Yours is pobably set to > "Leave as drawn within constraints" Choose any of the other two to get a different option - the task will probaly fall back to day 1. Best option is to put some logic onto it. Best regards Mike Testro
Member for
13 years 4 monthsThanks
Thanks
Member for
19 years 10 monthsHi Ronan Goto Tools > Options
Hi Ronan
Goto Tools > Options > Reschedule and you will see three options for tasks with no links.
Yours is pobably set to > "Leave as drawn within constraints"
Choose any of the other two to get a different option - the task will probaly fall back to day 1.
Best option is to put some logic onto it.
Best regards
Mike Testro