Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Asta Power v11 - Progress line not transferring when imported in P6 v 6.2

1 reply [Last post]
Emmanuelle Prefol
User offline. Last seen 5 years 7 weeks ago. Offline
Joined: 24 Nov 2011
Posts: 14
Groups: None

While progress line on a programme generated with Asta Power Project (APP) with v11 is @ 10/08/12. When file is saved as Primavera .xer and either re-opened in APP on in P6 V6.2, progress line/data date is changed to 24/03/12 which is actually the start of the project? What I should I be checlking?

Additionally, when programme either re-opened in APP on in P6 V6.2, start of in-progress activities are actualised in 2008/2009 and end dates brought back in?

Any ideas.

Replies

Mike Testro
User offline. Last seen 4 weeks 4 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Emmanuelle

The transfer between Asta and P6 is never perfect and small adjustments sometimes have to be made - particularly with calendars.

So i suggest you reset the progress line in P6 to the required date and check for any other peculiarities.

Best regards

Mike Testro