Asta PowerProject - Remove horizontal thick black line

Member for

19 years
Permalink

This may have been resolved by now but i suppose it will be helpful to anyone searching this topic. 

 

Where there is an unbroken horizontal line like that (i believe a page break is a dashed line?) it is where the ruling line properties have been modified for that bar to be shown thicker / bolder.

 

Right click on the chart on the bar below the line, press 'Ruling Lines.....' and a small window will open, go to the 'Specifics' tab and double click the box to the right of 'Appearance:' and another window will open, in this window you can change the formatting of the ruling line to match the rest of the chart.

Member for

19 years 10 months
Permalink

Hi K Yong

This could be the Page Break for printing.

Select the bar underneath the line and then go to Insert - Page Break - deselect.

Mike Testro