Hi Laurie



The easiest way is to set up your main programme as a "baseline" using the baseline wizard under the "file heading".



When you set up the Planned Percent Complete column you can select the results to come from the baseline programme.



You may need to go back to your first unprogressed programme to set up the 1st baseline and ten import it into your progressed charts.



Best regards



Mike Testro