Title Seeking information about TILOS

Hi

I am Nilesh.

I am working with a EPC Company (DODSAL-IN DUBAI ) where PRIMAVERA is being used for all purposes.

My company’s strength lies in Pipeline Projects and now we are doing a Rail Project also.

I am doing an analysis whether switching to TILOS would be beneficial or not.

Can I have views of all you expert guys on this.

Thanks & Regards

Nilesh

nilesh.dandale@dodsaldxb.ae

Groups:

Comments

Resource calculation in TILOS

Nilesh.

 

TILOS resource model is adapted to construction production planning and control:

Quantity and work rate on task level allow easy calculation of duration. Quantity gets used in resource calculation and based on production rate needed resources can be calculated. Reverse, one or more resources can set task work rate. Sample Mass Haulage:  Excavator sets productivity; TILOS calculate needed trucks based to move earth. If extra excavator or bigger is added, TILOS updated trucks automatically.

We have quantity, time and fixed assignements.

Quantity can be calculated even from distance profile imported from land surveying programs.

  can you tell me how to

 

can you tell me how to control resourse in tilos?

and how it is better than primavera.

 

Regards

Nilesh

  can you tell me how to

 

can you tell me how to control resourse in tilos?

and how it is better than primavera.

 

Regards

Nilesh

Tiols

 

Dear Mathew,

can you tell me how it work and how it is better than primavera.

we have pipeling project.

Linear Scheduling with TILOS: Time Location Software

Dear Nilesh,

 

those are the main points where TILOS and Primavera are different regarding linear projects:

1. In TILOS you can plan the activities according the needs of the location / site. Your plan is more accurate and covers all the problems and clashes that are invisible in Gannt Chart Structure.

2. With TILOS you can DISPLAY the schedule in a Time-Distance Chart with reference to the site plan and site information. That means: Most effective understanding and presentation of a linear project. Information like elevation and the location of stations and hindrances is naturally connected.

3. In TILOS you can progress not only time and quantities: You can also progress DISTANCE: That means: You directly see, which parts of your pipeline is finished, which parts are still to do and to which locations you have to come back later.

You can get some info about TILOS on pipeline projects here:

http://blog.tilos.org/general/the-concept-of-linear-scheduling-1/

and here:

http://blog.tilos.org/general/the-concept-of-linear-scheduling-2/

and here:

http://www.tilos.org/pipeline-construction.html

and here:

http://www.tilos.org/fileadmin/downloads/doc/WorldPipeline_TILOS_Article...

kind regards

Thorsten

Dear Matthew & matt, Thank

Dear Matthew & matt,

Thank you for reply,

but can you tell me any soild,strong thing about in TIOLS means we can do in tilos but we can not do  in primavera.

for linaer project.

and can we do linaer scheduling in primavera,

Dear Matthew & matt, Thank

Dear Matthew & matt,

Thank you for reply,

but can you tell me any soild,strong thing about in TIOLS means we can do in tilos but we can not do  in primavera.

for linaer project.

and can we do linaer scheduling in primavera,

NileshI agree with Matt, once

Nilesh

I agree with Matt, once you get used to using Tilos it will always be your first choice for linear projects.

Regards,

Bryan

Tilos

Nilesh

 

If you want to resource / baseline and control any linear project then Tilos is the real deal.

Regards

Matt

Tilos

Nilesh

 

If you want to resource / baseline and control any linear project then Tilos is the real deal.

Regards

Matt