Primavera

Hi Guys,

Can anyone suggest a reason why the original duration might be one day and the start and finish dates show as two days. See example below. 

Start: Oct 08th Finish: Oct 09th

 

Thanks in advance.

Comments

Check the Clalendar set for

Check the Clalendar set for the Activity. if the Calendar is set at four hour duration and original duration is 8 hours then it will show as 2 dates.

Market Place

For 25+ years, APMX has been providing competency based project management training to Fortune 500 companies around the world, applying the principles of project based learning, designed to produce measurable results, generating a favorable “return on training investment”.
See how the TIME - LOCATION - VIEW brings clearness to your work programmes
Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher and PMI accredited REP. Teach yourself using on-line or book based learning or run your own in-house or public PMI accredited courses.