Project Coordination

Planner/Scheduler , Pennecon Energy, Hebron GBS Project

START Date: 
July, 2013
END Date: 
July, 2014

Responsible for development, control and monitoring of titanium and 6Mo pipe fabrication schedule for Exxon Mobil’s Hebron project. Updating and tracking progress against baseline and reporting on the outputs. Other duties include creating fabrication workpacks, coordinating the coatings process and shipping to ensure timely site delivery. Deputised for the Project Manager during business and vacation absences.

Experience Hours (Planning & Scheduling): 
1700
Experience Hours (Cost Management): 
300

Project Engineer, Bayer HealthCare, Vitamins Workshops Upgrade / Process Washing Station / Bins Storage

START Date: 
July, 2004
END Date: 
December, 2005

- Working out a part of the Site

Experience Hours (Planning & Scheduling): 
500
Experience Hours (Cost Management): 
500

Project Control Specialist and Senior Planner/Scheduler , OPTI CANADA INC., Long Lake Upgrader Project (Joint Venture by OPTI Canada and Nexen)

START Date: 
April, 2004
END Date: 
October, 2005
Project schedule/cost control, support development of the Master U&O level-2 and level-3 schedule, progress monitoring, verification and reporting, schedule administration, project control of all OPTI Managed contracts ($20M, 399,000 hrs), manage schedule interfaces, review contractor's level IV activities, key milestones and baseline deliverables, integration of a commissioning and start-up schedule into the master schedule, provide inputs to PDNs with schedule impacts, coordinate the integration of contractor's schedule into one common integrated schedule, module fabrication and delivery mon
Experience Hours (Planning & Scheduling): 
2100
Experience Hours (Cost Management): 
500
Experience Hours (Forensic Analysis): 
650

Project Control Engineer, CTCI corporation, STEEL PLANT

START Date: 
September, 2013

·         Prepare the master schedule, area & department L4 schedule.

·         Control the schedule & covering up the delays with catch up schedule.

·         Progress Monitoring & Maintain Baseline schedule.

·         Time to time visit the site to check the progress.

Experience Hours (Planning & Scheduling): 
3200
Experience Hours (Cost Management): 
50
Experience Hours (Forensic Analysis): 
0

Senior Civil Engineer, Technofab Engineering Ltd., Buildings with all Utilities, Roads, Water,Drainage,Sewerage system

START Date: 
June, 2008
END Date: 
February, 2013

Construction project management,Planning & Scheduling,Construction site Execution Management, Supervision & Monitoring,Project Controls,Quantity Surveying,Billing,Contracts,Project Coordination, Site Deviation, Design Reviews, Reporting, Liaising,Documentation.

Project Control Engineer, Hatch Associates Pty Ltd, Koniambo Nickel Mining Project

START Date: 
June, 2012
END Date: 
May, 2013

Projects Executed

Ø    Koniambo Nickel Project – Construction of Nickel Refining Plant at Koniambo Massifs in New Caledonia (a 60,000-tonne-per-annum ore processing facility developed by a joint-venture partnership between Xstrata Nickel and SMSP New Caledonia. Hatch - Technip joint-venture is designing and constructing the project with Chinese & Korean companies (CMIIC, Doosan etc) as construction contractors.)

 

Major Responsibilities

Experience Hours (Planning & Scheduling): 
2000
Experience Hours (Cost Management): 
2000

Project Controls Engineer, ARCONS, Alkhalij Power Plant - Sirt Libya

START Date: 
December, 2009
END Date: 
July, 2012

• Reviewing and studying contract agreement.
• Preparation of Method Statement for Erection of steel structure and tanks.
• Preparation of master and detailed project schedule (Primavera P6).
• Updating and follow up project schedule.
• Preparation of Daily, Weekly & Monthly Progress Reports.
• Preparation and follow up Material Control System.
• Control and follow up of monthly payments.
• Coordination and control of all incoming and outgoing e-mails and letters from and to the client.

PLANNING COORDINATOR, Mancon Consutlancy and Project Management , Mantrac Takoradi New Facility-Ghana

START Date: 
July, 2012
END Date: 
June, 2013

* Preparing master and detailed time schedule (using primavera P6 and MS Project).
* Coordination with design team to prepare tender package
* Evaluation and awarding of contractors.
* Preparation of contract agreements complying with FIDIC standards.
* Preparation of projects budget.
* Following up construction phase (time and cost).
* Coordination with different project parties (emails - meetings).
* Document controlling (project documents - historical data - lessons learned)

Planning / Senior Planning / Project Engineer, Leighton Welspun Contractors Pvt. Ltd., DLF - The Camellias

START Date: 
June, 2013

1. Formulate Work Break Down structure for the project.

2. Collect all inputs related to project plan prepration by areas from respective managers on project task force and prepare the base plan.

Planning / Senior Planning / Project Engineer, Leighton Welspun Contractors Pvt. Ltd., DLF - The Camellias

START Date: 
June, 2013

1. Formulate Work Break Down structure for the project.

2. Collect all inputs related to project plan prepration by areas from respective managers on project task force and prepare the base plan.